Construction Works 11 November to 25 November

11 November to 25 November

  • Demolition works on all floors internally
  • Demolition of the existing flat roof
  • Press mouldings to be taken of the existing Hall cornice detailing
  • Careful removal of the Hall ceiling
  • Banner installation, above Church Court Archway (09/11)
  • Forming new structural openings and installing temporary works supports on all floors
  • Enabling works for the crane on the South terrace
  • Internal scaffold crash deck within library to facilitate roof demolition
  • Demolition of existing slab and adjacent walls to facilitate the formation of a new lift pit in the north façade lightwell
  • Concrete work to support the new steel roof structure

Construction Noise

Location Description of the Works Noise Level

Roof – Flat Roof - 11-25 November 2019

  • The removal of the flat roof structure to allow new structural steel to be installed, North East Corner

Amber

Ground Floor – North Facade - 11-25 November 2019

  • Demolition of Small Masonry Staircase down to Low Level, North

Amber

Basement – Lightwell - 11-25 November 2019

  • Demolition works in the lightwell to facilitate the construction of a new lift shaft, North East Corner
  • Demolition of concrete slab for new escape stair, adjacent to lightwell

Red

Mitigation Measures

  • Installation of Noise Reducing Acoustic Blankets:
    • At door openings
    • At all windows locations
    • Above the works in the lightwell
  • Works to be undertaken during Noisy Hours only
  • Hand tools will be used to demolish the walls, as far as reasonably
    practicable.

We're Building Something New

Please take a look at this short video to hear the rationale behind the project and see some of its design features

play_arrow pause

0:00

-0:00

volume_up volume_down volume_off
zoom_out_map

Contact Us

Sir Robert McAlpine Special Projects Logo

SRM Special Projects Site Team offices are located within the Inn’s former Treasury Office, with access from the South Terrace where Reception Entrance signage can be found on the hoarding to assist. Please press the bell to attract attention.

Site working hours will be from:

8.00am - 6.00pm Monday-Friday
9.00am - 2.00pm Saturday

John Walker

Project Manager, SRM Special Projects

John Walker

Project Manager, SRM Special Projects

John Walker

Project Manager, SRM Special Projects

Address

The Honourable Society of the Inner Temple

Treasury Office,

London EC4Y 7HL

Education

020 7797 8208