Construction Works 18 November to 2 December

18 November to 2 December

  • Demolition works on all floors internally
  • Demolition of the existing flat roof
  • Removal of existing flat roof structural steel
  • Press mouldings to be taken of the existing Hall cornice detailing
  • Careful removal of the Hall ceiling
  • Forming new structural openings and installing temporary work supports on all floors
  • Internal scaffold crash deck within library to facilitate roof demolition
  • Demolition of existing slab and adjacent walls to facilitate the formation of a new lift pit in the north east lightwell
  • Concrete work to support the new hall roof
  • Removal of existing lifts
  • Installation of library façade restraints

Construction Noise

Location Description of the Works Noise Level

Basement – NW Lightwell - 18 November-2 December

Piling for new escape stair, adjacent to lightwell

Green

Roof – Flat Roof - 18 November-2 December

  • The removal of the flat roof structure to allow new structural steel to be installed, North East Corner

Amber

Basement – NE Lightwell - 18 November-2 December

  • Demolition works in the lightwell to facilitate the construction of a new lift pit, North east
    Corner

Red

Piling for new escape stair, adjacent to lightwell

  • Demolition of an existing plinth in the basement plant room, adjoining Francis Taylor Building
    party wall.

Red

Mitigation Measures

  • Installation of Noise Reducing Acoustic Blankets:
    • At door openings
    • At all windows locations
    • Above the works in the lightwell
    • Against party walls
  • Works to be undertaken during Noisy Hours only
  • Hand tools will be used to demolish the walls, as far as reasonably
    practicable.

We're Building Something New

Please take a look at this short video to hear the rationale behind the project and see some of its design features

play_arrow pause

0:00

-0:00

volume_up volume_down volume_off
zoom_out_map

Contact Us

Sir Robert McAlpine Special Projects Logo

SRM Special Projects Site Team offices are located within the Inn’s former Treasury Office, with access from the South Terrace where Reception Entrance signage can be found on the hoarding to assist. Please press the bell to attract attention.

Site working hours will be from:

8.00am - 6.00pm Monday-Friday
9.00am - 2.00pm Saturday

John Walker

Project Manager, SRM Special Projects

John Walker

Project Manager, SRM Special Projects

John Walker

Project Manager, SRM Special Projects

Address

The Honourable Society of the Inner Temple

Treasury Office,

London EC4Y 7HL

Education

020 7797 8208