- Soft strip / Demolition to all floors internally
- Demolition of existing Flat roof structures
- Press mouldings of the existing Hall cornice detailing being taken
- Careful removal of the Hall ceiling
- Asbestos removal
- Forming new structural openings and installing temporary works supports on all floors
- Enabling works for the crane on the South terrace
- Internal scaffold crash deck within library to facilitate roof demolition
- Demolition of existing slab and adjacent walls to facilitate the formation of a new lift pit in the north façade lightwell
- Installing concrete supports for new structural steelwork above hall
- Installation of final banner sections (9 November 2019)
Construction Works 4 November to 18 November
4 November to 18 November


Removal of the Existing Flat Roof


Concrete Works for the Mobile Crane
Construction Noise
Location | Description of the Works | Noise Level |
---|---|---|
Roof – Flat Roof |
The removal of the flat roof structure to allow new structural steel to be installed, North East Corner |
Amber |
Ground Floor – Gents WC |
Demolition of Small Masonry Staircase down to Low Level, North |
Amber |
Basement – Lightwell |
Demolition works in the lightwell to facilitate the construction of a new lift shaft, North East Corner |
Red |
Mitigation Measures
- Installation of Noise Reducing Acoustic Blankets:
- At door openings
- At all windows locations
- Above the works in the lightwell
- Works to be undertaken during Noisy Hours only
- Hand tools will be used to demolish the walls, as far as reasonably
practicable.
We're Building Something New
Please take a look at this short video to hear the rationale behind the project and see some of its design features
0:00
-0:00
Contact Us
SRM Special Projects Site Team offices are located within the Inn’s former Treasury Office, with access from the South Terrace where Reception Entrance signage can be found on the hoarding to assist. Please press the bell to attract attention.
Site working hours will be from:
8.00am - 6.00pm Monday-Friday
9.00am - 2.00pm Saturday

John Walker
Project Manager, SRM Special Projects
Detailsnavigate_next
John Walker
Project Manager, SRM Special Projects

John Walker
Project Manager, SRM Special Projects
Detailsnavigate_next
John Walker
Project Manager, SRM Special Projects

John Walker
Project Manager, SRM Special Projects
Detailsnavigate_next
John Walker
Project Manager, SRM Special Projects
Address
The Honourable Society of the Inner Temple
Treasury Office,
London EC4Y 7HL